Commercial Screw Piers
Westmead Catholic Education Precinct, Stage 1
Geotechnical Ground Conditions:
Carried out by Jefferey & Katauskas P/L
Client:
Zadro Constructions
Foundation Solution:
Originally approx 300off conventional concrete bored piles designed. To limit risk of construction issues associated with a variable water table and contaminated ground Australian Foundation Systems installed approx 300off screw piles with loads varying from 300kn-750kn. Screw pile suitability confirmed via means of a static load testing on site as shown below.
Site Location:
Darcy road, Westmead NSW
Testimonial:
Australian Foundation Systems provided the alternative design and drove the concept prior to contract award. They then completed the works on site professionally and on time.
Bill Moller (Site Manager)
AFS Residential piering about to announce major new signing............ Stay tuned!